Alfreton – Test Facility

Alfreton – Test Facility

The project was to create a Test Facility between 4 manholes using 900m, 450mm & 300mm diameter pipes.

AGL works included the following activities:

  • Site survey and setting out for the works
  • Excavate trenches for pipe lines & manholes
  • Install manhole bases
  • Install 1200mm, 1500mm and 1800mm vertical precast concrete Manholes
  • Install 300mm, 450mm and 900mm drainage pipes
  • Install ramp access
  • Install Scaffolding around 4 no manholes
  • Install new hardstanding road and car parking area

Key details

Client

Radius Subterra

Service Provided

Principal Contractor

Location

Alfreton